The 2015 Town Sidewalk Replacement Project for the demolition, sub-grade preparation and flatwork to replace the existing sidewalk(s) on the south side of Fourth Street between North Fork Avenue and Poplar Street within the Town will begin on Monday, July 6, 2015. The project will take about 3 weeks to complete.
C & N Construction, Inc. of Delta (Chris Serve) is the contractor for the project. C & N’s bid for the project was awarded by the Town Board at a cost of $21,578.60.
The sidewalk work consists of the demolition of the existing concrete sidewalk in place, preparation of subgrade and flatwork necessary to install concrete sidewalk in accordance with the Town’s specifications.
To maintain safety throughout the construction zone, C & N will place all traffic controls signs, barricades and other devices during the total construction time of work, including time for concrete curing. Temporary fencing or other adequate measures to control pedestrian access to the work area shall be maintained.
If you would like more information about the project please contact Town Hall, Monday through Friday, from 8:00AM to 4:30 PM with your questions or concerns.